Chemical plant Hammerfest
Complete installation of bulk facilities for NorSea Polarbase
During 2025, Marine Support delivered the complete installation of a MID-approved chemical plant at NorSea Polarbase in Hammerfest. The installation included:
4 insulated and heated tanks of 250m3 for storage of one product
2 insulated and heated tanks of 188m3 for storing two additional products
Pump house with technical installation, as well as import and export points
Dock house with import and export points
Pipes from tank farm to quay in chemical-resistant PE
Electrical and automation for fully automatic operation